RenewableUK hosted a pre-All Energy
workshop that reported SI Ocean's work to date, and discussed
interaction between the supply chain and the wave and tidal sector.
Several reports were unveiled:
- David Krohn (RenewableUK) gave a summary of RenewableUK's recent report on the sector, alliteratively entitled: 'Conquering challenges, generating growth'.
- Henry Jeffery (University of Edinburgh) announced SI Ocean's technology status report, and asked for comments and feedback.
- Clare Hamner (Carbon Trust) announced SI Ocean's cost of energy report and also asked for feedback. In particular, she asked whether the forecast cost of energy with 1GW of installed capacity was viable.
In the supply chain discussion, there
was a real sense of urgency in getting the sector off the ground.
Conflicting viewpoints were expressed. Sometimes this lead to insight
and consensus; sometimes to an almost tangible frustration about
impasses lying on the road ahead.
'This unique window might not
deliver'
Abbie Badcock-Broe (IT Power) summed up
the sense of urgency with the words above. Andrew Jamieson (Offshore
Renewable Energy Catapult) warned that the prize of a marine
renewables industry based in the UK was not to be taken for granted:
he declared that 'the risk of underachievement is real', and
cautioned against complacency: 'the world will overtake us'.
Rob Saunders (TSB) described the support offered by the TSB as
'timely intervention'.
One reason for this sense of urgency is
the uncertainty caused by the recent reassessment of the size of the
industry. Clive Adshead (SMD) reminded the audience that as recently
as 2008, the forecast for wave and tidal capacity was 1.3 GW by 2020.
The allure of a slice of a ~£5 billion pie resulted in a supply
chain hungry to find ways to add value to the industry. Clive
believed the forecast in the recent
RenewableUK report was more realistic: ~140 MW by 2020, with
favourable contract for difference support. This latest forecast
meant there was 'not enough likely installed capacity to make a
business case' and as a result, SMD had delayed building
prototypes of equipment developed for the wave and tidal industry.
Clive warned that it was 'paramount that the latest predictions
(installed capacity) are met – if they are missed this time around,
the industry will not get the backing of the supply chain'.
Impasse #1: A toolbox for the first arrays
The need to stick to the schedule for
installing the first arrays sets the scene for impasse #1. Joury Van
Gijseghem (DBE) described this as a 'chicken or egg'
situation: we need a toolbox to
build the industry, but we need an industry to make building the
toolbox bankable. His suggested solution was to build the
first arrays without specialist installation equipment, and focus
simply on getting 'something into the water'.
Ferdinand Dees (Mojo Maritime) shared
his experience of doing just that. When installing something in a
tidal race, apparently 'the ROVs took themselves out', so they
used divers instead. He concluded that without the right tools in the
toolbox, 'it is not safe; it is not efficient'. Abbie (IT
power) went further to warn that rushed installation was a
threat to the industry. She suggested that we are trying to run a
'long distance marathon when we can barely walk' (project
development in tandem with technology development), and that
this shifting of priorities away from the natural technology
development process could inhibit innovation.
Clive (SMD) suggested another way to
end this impasse: better engagement between the providers and end
users of specialist equipment. He said SMD prototype the
installation equipment they had designed if there was enough
commitment from potential customers. He highlighted the potential
problem of each developer asking the supply chain for different
customised components: 'the non-recurring engineering is the
expensive bit'. He called for more collaboration to prevent this;
not only between developers and contractors, but within the supply
chain industry itself. Joury (DBE) agreed that early contractor
involvement was important.
Another impasse bypass suggested by
Clive was to have a 'business strategy based on products, not an
industry'. This suggests that SMD are considering co-funding
development of tools for the marine renewables industry by
identifying markets for these tools in established industry.
Impasse #2: Cats and seagulls
There was much
audience discussion about collaboration. Everyone agreed it was
desirable but difficult. Andrew (Catapult) expressed frustration that
while there was plenty of talking about it, 'the doing was like
herding cats'. Ownership of new intellectual property (IP)
generated collaboratively appeared to be a stumbling block. Clive
(SMD) offered the charming image of the seagulls from 'Finding
Nemo' crying 'Mine! Mine! Mine!'
Ferdinand
(Mojo) suggested we should forget about the IP and simply get on with
making things. However, he recognised that this was easier for larger
companies. Jeremy Smith (QED Naval) agreed with this, saying that
they 'used IP as a tool
to talk to the big guys',
and suggested gentleman's agreements be made about IP. After the
talk he explained this comment to me: he was referring to the
importance of respecting
the context of the IP.
He
felt that any barriers to collaboration would slow or hinder
development of the industry, and suggested that the corporates 'work
with the SME to develop the product or license the ideas... so the
industry can benefit and grow to its full potential rapidly'.
Abbie (IT Power) who works for a consultancy assisting technology developers, didn't think IP could be shared. She later explained to me that although IP was not an issue for IT Power, many of their customers were keen to retain IP. Michael Betschart (Andritz Hydro
Hammerfest) said that his company was happy to collaborate on enabling technologies, and had no interest in the resulting IP, but that there were strategic development areas where they did not want to collaborate. David (RenewableUK) recounted how a new company
brought out a tidal turbine that was very similar to an existing
technology, and noted that this did not harm the more established
company. This anecdote suggested that IP is not the only thing that
determines the value of a small technology company.
Impasse #3: Who shoulders the risk?
Another stumbling block for
collaboration is the question of who bears the risks for the first
arrays. Michael (Hammerfest)
summarised the problem: investors are not willing to take the risk of
a 10MW project, and it is hard to find a supply chain that will bear
that risk. Andrew (Catapult) said that 'there
is no magic wand' for
this problem, and noted that objectivity about risk was required to
overcome this impasse.
Clive (SMD)
questioned ownership of supply chain equipment such as drill rigs. It
is particularly difficult to decide who bears the cost of this
equipment, as there is uncertainty about the size of the future
market. He suggested a consortium of all the project partners to
share the risks and costs.
There were a
couple of speakers who addressed risk reduction. John Watson (NAREC)
gave a talk on how NAREC could support risk reduction: accelerated
lifetime testing, checking component integration, and practising O&M
manoeuvres in order to reduce times. Rob Eavis (PolyGen Limited)
suggested that costs and risks could be reduced by replacing steel
tubes with polymer tubes. The lack of corrosion and fatigue would
reduce the need for over-engineering. He listed other advantages,
such as an existing mature supply chain, existing marine applications
(Salmon farms), neutral buoyancy and low friction surfaces.
Uncertainty about point of entry
There was some discussion about the way
forward. Henry (UoE) said it was 'not the responsibility of the
supply chain' to find solutions to these impasses. Ferdinand
(Mojo) bemoaned the lack of a concerted European push, lead from
above, to facilitate collaboration. Henry thought that nevertheless
there would be support at EU
level for collaborative projects if 'an organisation went to
them with a solution'. Charlie Blair (Carbon Trust) said that the
Carbon
Trust was working on getting utilities together to work on
innovative technologies. Rob Sanders (TSB) gave a talk on how the TSB
was supporting collaborative projects. The focus is now moving to
system support and enabling technologies, and they are planning a
funding call at the end of this year for offshore energy
infrastructure. Rob noted that better use could be made of the SMART
scheme. He also highlighted Eurostars
as a funder of cross European collaboration. Andrew (Catapult) said
that it was within the Offshore
Renewable Energy Catapult's remit to facilitate collaboration
between the UK supply chain and the marine renewables industry. He
expressed a strong commitment to supporting wave and tidal, and
appealed to the supply chain to get involved.
Learning from the offshore wind industry
There were a couple of interesting
references to the offshore wind industry. Clive (SMD) cited the
offshore wind industry as an example of how not to engage the supply
chain: a gap analysis by the Crown Estate identified installation as
a high risk area, yet Clive was not aware of anyone in the sub-sea
installation supply chain being asked by the offshore wind industry
how to assess and mitigate the risks of installation. Joury (DBE)
said there was much to be learnt about expectations. With GW of wind
installed onshore, it was thought that moving offshore would be easy.
However, more work was required to marinise wind turbines than
initially thought. He concluded that it was unrealistic to think that
wave and tidal could be brought to maturity quickly. Henry (UoE) said
wave and tidal would have to work harder than offshore wind at
getting costs down.
Abbie (IT Power) noted that when looking for
solutions, we often refer to oil and gas, and offshore wind. However,
wave and tidal are different. She concluded that we need innovative
ways of thinking, and alternative ways of working together: we can't
afford to be greedy.
Comments on the main conference (All Energy Opportunities 2013):
http://www.wavepowerconundrums.com/2013/06/aeo-fundamental-challenges.html
http://www.wavepowerconundrums.com/2013/06/aeo-trends-and-titbits-cost-of-energy.html
http://www.wavepowerconundrums.com/2013/06/aeo-trends-and-titbits-commercialisation.html
Comments on the main conference (All Energy Opportunities 2013):
http://www.wavepowerconundrums.com/2013/06/aeo-fundamental-challenges.html
http://www.wavepowerconundrums.com/2013/06/aeo-trends-and-titbits-cost-of-energy.html
http://www.wavepowerconundrums.com/2013/06/aeo-trends-and-titbits-commercialisation.html
Image credit:
'Bored at work, so I made a giant duck attack a seagull', by Karin Z:
http://imgur.com/ulgyLEg. Observant readers will recognise the duck as Florentijn Hofman’s Rubber Duck project.
No comments:
Post a Comment
Comments
Note: only a member of this blog may post a comment.